Early completion of the piling is a splendid achievement by contractor Tulloch Developments and very timeous before the weather broke with autumn gales. The new jetty is already providing a significant shelter improvement. The overall project is due for completion one year from now. John Coutts took the excellent photograph giving a good impression of the 805 metres (half an imperial mile) of quay walls that are now installed.