Largest-ever capital project enhances harbour capacity and supports future growth.
Marine works on Lerwick Harbour's £24 million capital dredging project have been successfully completed, marking a major milestone in the largest capital investment in the port's modern history.
Lerwick Port Authority’s largest capital project to date involved the removal of just under 1 million tonnes of dredge material to deepen and widen key areas of the harbour, increasing capacity for larger vessels and supporting future growth across Shetland's fishing, cruise and offshore industries.
Capt. Calum GrainsChief ExecutiveCaptain Calum Grains, Chief Executive of Lerwick Port Authority, said: "The completion of the marine works is a significant milestone for Lerwick Harbour and represents an important investment in the port's long-term future.
"This project has been about ensuring we have the infrastructure and capacity to meet the changing needs of the industries we serve. By improving access and accommodating larger vessels, we are creating new opportunities across several key sectors while strengthening Lerwick's role in supporting Shetland's economy.
"Delivering a project of this scale within a busy working harbour has required considerable planning and collaboration. We are grateful to everyone involved in bringing the marine works to a successful conclusion."
The dredging works have widened the North Ness Channel to 140 metres and deepened it to 10 metres, while providing a continuous 10-metre berth depth along the 275-metre Mair's Pier and improving the approaches to Gremista Quay.
At Dales Voe, dredging has increased the depth adjacent to the quay to 14.5 metres, with approaches deepened to 16 metres, enhancing the harbour's ability to accommodate larger offshore vessels strengthening Lerwick's position in the offshore industry, supporting larger vessels, onshore decommissioning and marine operations associated with offshore exploration, development and production.
For the fishing sector, improvements will enable future infrastructure quay developments at Gremista to support pelagic sector capacity.
The cruise sector will also benefit from improved navigational access through the North Ness Channel and central basin, alongside consistent 10-metre water depths at Mair's Pier, creating opportunities for larger cruise ships to use the 275-metre quayside.
The project was managed by Arch Henderson LLP, a company of Haskoning, with specialist contractor Boskalis Westminster Ltd undertaking the dredging works.
Andy Sandison, Senior Consultant, Arch Henderson said: "We are delighted to have provided full design, consenting, tender procurement and project management working with Boskalis Westminster Ltd and the Authority to manage both the challenging ground conditions requiring trailer suction, drill and blast and back-hoe dredging techniques while also complying with strict environmental consenting conditions relating to marine protected species within the harbour."
Paul de Jong, Managing Director of Boskalis Westminster Ltd said: “We are proud to have completed a second major dredging project for Lerwick Port Authority. Working closely with the teams at Lerwick Port and Arch Henderson, we successfully delivered a challenging scheme to deepen the North Harbour and Dales Voe.
With all our vessels now safely on their way to their next projects, we would like to thank all parties involved for the excellent collaboration.
We look forward to the opportunity to work in Shetland again in the future.”
The project is supported by Bank of Scotland and Scottish Government agency Highlands and Islands Enterprise.
Scott Joyce, Relationship Director at Bank of Scotland, said: “Completing the dredging work is an important milestone for Lerwick Harbour and will help the port pursue new opportunities in the years ahead.
“We’re proud to have supported Lerwick Port Authority on the project and look forward to seeing the benefits for the port and the wider Shetland economy.”
The operation involved a specialist fleet of dredging and support vessels, with final checks completed ahead of the departure of the main vessels on 31 October. In total, the two phases involved the removal of soft seabed material and hard rock, with material disposed of north of the island of Bressay.

Dredging operations at Dales Voe, where Boskalis Westminster Ltd has completed Lerwick Harbour’s largest-ever capital dredging project. Photo by Alexander Simpson.