Port's biggest project yet boosts Shetland activity. Lerwick Port Authority has welcomed the largest offshore structure yet to be decommissioned at the deep-water Shetland port.

Delivery of the 14,200 tonne Ninian Northern platform topside today (Friday, 28 August 2020) also marks the inauguration of a new, heavy-duty decommissioning pad at Dales Voe Base where the facility has been developed by Lerwick Port Authority, expanding the capability to keep UK sector decommissioning projects in the UK.

Lerwick, Shetland: Pioneering Spirit, the world’s largest construction vessel, arrives in Dales Voe with the 14,200 tonne Ninian Northern topside for decommissioning. Credit: Rory Gillies/Shetland Flyer Aerial Media.

Lerwick, Shetland: Pioneering Spirit, the world’s largest construction vessel, arrives in Dales Voe with the 14,200 tonne Ninian Northern topside for decommissioning. (c) Rory Gillies/Shetland Flyer Aerial Media.

The topside was removed in a single lift by Allseas’ Pioneering Spirit, the largest and most sophisticated construction vessel in the world, and transported to Lerwick on her first arrival into a UK port.The Ninian oilfield is located around 100 miles (88 nautical miles) north-east of Shetland.

The transfer by Allseas’ cargo barge, Iron Lady, to the decommissioning pad, is the first complete northern North Sea topside load-in at Lerwick. Dismantling by leading contractors, Veolia/Peterson, with a 97% recycling target, will create and sustain jobs and investment in the local economy.

Lerwick Port Authority Chief Executive, Captain Calum Grains, said: "The arrival of the Ninian Northern topside at our Dales Voe Base is a welcome boost to activity in Shetland amidst the Covid-19 downturn and another very important stage in the development of Lerwick's reputation as an active, leading centre for decommissioning.

"The pad is a significant addition to our unique quayside infrastructure, not only as a catalyst for handling larger offshore structures, but also in attracting the interest of the renewables sector for future projects, particularly floating offshore wind developments.

“The scale of the topside, the single-lift delivery and the infrastructure already in place adds weight to the widely-accepted case for Lerwick to be the location of an Ultra-Deep-Water Quay in the UK for even bigger projects in the competitive international decommissioning and renewables industries. The proposal has strong Government and industry support."

The Port Authority’s vision for the future to allow bigger, deeper-draft vessels to berth, includes further dredging at Dales Voe to complement the planned Ultra-Deep-Water Quay.

Investment by the Port Authority has been backed by the Scottish Government, Highlands and Islands Enterprise and Bank of Scotland who have provided financial assistance for the quay development at the base, as well as the decommissioning pad.

Paul Wheelhouse MSPScotland's Energy Minister

“The arrival of the Ninian Northern topside in Shetland is further evidence of the strength of Scotland’s decommissioning supply chain and the capabilities, knowledge and skills held within the industry.

“I am delighted to see how recent investment at Dales Voe by the Scottish Government has been used by Lerwick Port Authority and its partners to increase the decommissioning potential of the port and help secure major decommissioning projects.

“Looking forward, the Scottish Government remains committed to establishing an Ultra-Deep Water Port at Dales Voe to unlock even more opportunities for decommissioning of top-sides and other oil and gas infrastructure by allowing the site to accommodate the largest heavy lift vessels currently in operation in the North Sea. This allows projects that currently cannot be decommissioned in Scotland, due to the lack of a deep water facility, to be retained here for dismantling in Shetland or for partnerships to allow the dismantling of some modules at other decommissioning facilities across Scotland.”

Paul Wheelhouse MSP
Scotland's Energy Minister
Audrey MacIverDirector of Energy and Low Carbon for Highlands and Islands Enterprise

The foresight and commitment by Lerwick Port Authority to invest in critical infrastructure continues to bring benefits to Shetland and the wider Scottish supply chain. This latest arrival is particularly timely given current challenges being faced by the oil and gas industry and the associated supply chain.

“Building on existing strengths and expertise, Dales Voe is firmly establishing itself as a key UK facility for serial, large scale offshore decommissioning, ensuring Shetland continues to play an ever increasing role in the country’s energy transition.“

Audrey MacIver
Director of Energy and Low Carbon for Highlands and Islands Enterprise

The decommissioning pad, designed and project-managed by Arch Henderson and constructed by local company, Tulloch Developments, has an impermeable surface and a 60 tonne per square metre load which matches the quayside capacity. Unique to the quayside design is an 800 tonne per metre line loading for transfer of the topsides from the barge across the quayside.

The twin-hulled Pioneering Spirit is 382 metres long and 124 metres wide. A bow slot, 122 metres long and 59 metres wide, enables her to move around a platform and lift and transport entire topsides using eight sets of horizontal lifting beams. A 5,000 tonne special-purpose crane is used for lifts, such as lighter topsides. She also undertakes jacket removal and installation.

Watch: Pioneering Spirit arriving at Lerwick